The short answer
If panels sit on the part of the roof being replaced or restored, they have to come off first and go back on afterwards. In NSW, removing part of an electrical installation is electrical wiring work, which needs an electrical licence “regardless of the cost of the work”. Our advice is to have a licensed electrician, ideally your original solar installer, isolate and disconnect the system, lift and store the panels, refit them after the roof work, test it and issue a Certificate of Compliance for Electrical Work. We found no Sydney business that publishes a price; the clearest published figure is interstate.
Who can remove and refit solar panels in NSW
The NSW Government’s licensing page says “You must have an electrical licence or certificate before you can do any electrical wiring work in NSW, regardless of the cost of the work”, and defines electrical wiring work as “installing, repairing, altering, removing, or adding to an electrical installation”. NSW Fair Trading says installing panels “must be undertaken by either a licensed builder or a licensed electrical contractor”, and that the wiring must be done by a licensed electrical contractor or under a qualified supervisor.
After the refit, the electrician who tests the system must lodge a Certificate of Compliance for Electrical Work (CCEW) “no later than seven days after the electrical test”. No NSW source we found says whether a roofer may lift panels once an electrician has isolated them, so our advice is to arrange the removal and refit through a licensed electrician, and have the roofer quote for the roof only.
Accreditation is a separate thing: since 2024, Solar Accreditation Australia, not the Clean Energy Council, accredits solar installers for government rebates. The licence that matters for the wiring is the electrical licence.
Why solar panels are live even when switched off
The NSW Rural Fire Service’s protocol for firefighters puts it plainly: “During daylight hours a solar system will continue to generate electricity even if the system is shut down”, and “Wires between solar panels and isolator switches may still be live even when the isolator has operated.” It adds that only a solar-qualified electrician can confirm an array is fully isolated, “as this requires disconnection of wiring from the Solar panels”.
SafeWork NSW lists falls, contact with electricity, asbestos and falling panels among the risks of rooftop solar work, and its installation guide says “The carrying of panels by workers up ladders is not a safe system of work and must not be conducted.” Don’t climb up to help, and don’t touch panel cabling. SafeWork NSW treats a risk of a fall of more than 2 metres as high-risk construction work.
Planning rules for putting solar panels back
Rooftop solar on a house is exempt development, with no council approval, under section 2.41 of the Transport and Infrastructure SEPP when it meets that section’s standards. No clause deals with refitting an existing system, so by our reading the same standards apply when panels go back on:
- installed to the manufacturer’s specifications or by a Solar Accreditation Australia accredited installer, with no reduction in the building’s structural integrity and no structural alterations
- in a residential zone, on a roof facing a primary road, no more than 0.5 m out from the roof; on other roofs, no more than 1 m out, and at least 1 m from the boundary if more than 0.5 m out
- where the land has a heritage item or is in a heritage conservation area, not visible from a primary road at any point where the road meets the property boundary, and no more than 0.5 m out
So an array visible from a primary road where the road meets the property boundary, on land with a heritage item or in a heritage conservation area, isn’t exempt: check with council before it goes back on. The re-roof itself has its own rules: see council approval to replace a roof.
From 23 November 2026, new and upgraded rooftop solar in Ausgrid’s network has to be commissioned through the NSW CER installer portal. Energy NSW doesn’t say whether refitting the same system counts, so ask your electrician whether any network notice or approval is needed.
Solar warranties when panels are moved
Warranty terms on panels, inverters and mounting rails differ by brand, and some manufacturers’ terms exclude products that have been moved or reinstalled, or require reinstallation by an installer they nominate. Before anything comes off, check your warranty documents and ask your original installer how to keep the warranty intact. Ask about the inverter too: it may only need switching off and isolating rather than removing.
Solar panel removal and reinstallation cost
We found no Northern Beaches or Sydney business that publishes a price for taking panels off and putting them back. The clearest published figure is from Queensland: a Brisbane and Gold Coast roof restoration contractor says temporary removal and refitting by licensed solar electricians costs “around $120 per panel +GST” for a single-storey home with a standard set-up, and that double-storey homes or systems with micro-inverters “will often cost more”. The same page, updated 30 July 2026, also shows a lower figure of “around $85 per panel +GST”, so treat both as a rough interstate guide only.
To compare quotes, ask each one to say:
- who disconnects and isolates the system, and who refits, tests and issues the CCEW
- whether the rails and cables stay on the roof or come off
- where the panels are stored during the roof work
- whether broken tiles around the brackets are replaced
- whether new rails, clamps or brackets are needed for the new roof, such as moving from tiles to Colorbond
- the access allowance for a two-storey or steep roof
Roof prices themselves are in our roof replacement cost and roof restoration cost guides.
Common questions
Do solar panels have to come off to replace a roof?
Where they sit on the part of the roof being replaced, yes: the roof sheets or tiles under them can’t be changed with the panels in place. On a restoration, it depends on whether the panels cover the area being cleaned, repaired and coated.
Can a roofer remove solar panels in NSW?
Removing part of an electrical installation is electrical wiring work, which needs an electrical licence “regardless of the cost of the work”. No NSW source we found says whether a roofer may lift panels after an electrician has isolated them, so arrange the removal and refit through a licensed electrician.
How much does it cost to remove and reinstall solar panels?
We found no Sydney business that publishes a price. A Brisbane and Gold Coast roof restoration contractor (Queensland, page updated July 2026) publishes “around $120 per panel +GST” for a single-storey home with a standard set-up, and the same page also shows around $85 a panel +GST. It says double-storey homes and micro-inverter systems often cost more.
Do I need council approval to put solar panels back after re-roofing?
Usually not on a house, if the system meets the exempt standards in section 2.41 of the Transport and Infrastructure SEPP, including installation to the manufacturer’s specifications or by a Solar Accreditation Australia accredited installer, and protrusion limits. Where the land has a heritage item or is in a heritage conservation area, a system visible from a primary road where the road meets the property boundary isn’t exempt, and the system can’t protrude more than 0.5 m from the building.
Where this information comes from
The prices, rules and advice on this page come from these published pages, checked on 23 October 2026.
- NSW Government: electrical work licence · NSW Government licensing page, updated 23 June 2026
- NSW Fair Trading: guide to solar panels · NSW Fair Trading and Building Commission NSW homeowner guide
- NSW Fair Trading: solar panel installers, compliance and regulation · NSW Fair Trading, updated 19 October 2026
- NSW Government: electrical compliance requirements · Building Commission NSW, updated 19 October 2026
- Clean Energy Regulator: Solar Accreditation Australia · Australian Government regulator, updated 9 October 2024
- NSW Rural Fire Service: operational protocol for incidents involving photovoltaic arrays · NSW agency protocol, approved December 2022
- SafeWork NSW: solar panel retail and installation · NSW work health and safety regulator
- SafeWork NSW: guide to safe solar panel installation · NSW work health and safety regulator guide, February 2021
- SafeWork NSW: Code of Practice, managing the risk of falls in housing construction · NSW work health and safety regulator, approved code of practice, August 2019 edition
- State Environmental Planning Policy (Transport and Infrastructure) 2021: sections 2.20 and 2.41 · NSW planning law, version in force from 11 September 2026
- Energy NSW: NSW CER installer portal · NSW Government, updated 20 October 2026
- Oz-Roof: temporary solar panel removal for roof restoration · Brisbane and Gold Coast roof restoration contractor (Queensland), updated 30 July 2026